A few weeks ago, we completed a project in collaboration with our partner Elektromont Brno for our customer Siemens. During this project 10 employees worked together for 7 weeks at Recycling Kombinatie Reko B.V. in Rotterdam. During this collaboration, they took care of the following activities:
✅ Installation of cabletrays;
✅ Laying, bundling and labeling of cables;
✅ Connection work of control cabinets, junction boxes, cable glands and 110 V DC batteries;
✅ Testing work of all the cables.
All this for a steam turbine located in a turbine hall. The project has been successfully completed, which of course had to be celebrated. We would like to thank Siemens, Elektromont Brno and our employees again for the great cooperation!